Change history

Change history

Starting from Datahub version 2.6, we provide a detailed list of all version-specific changes to the documentation.

In the documentation for this upcoming version, all pages that include version-specific changes also have the corresponding Datahub version label (versio-2_7). The list includes all modified pages in the new version.

The labels are in Finnish. ‘versio’ = version, ‘kehitysehdotus’ = development proposal.

Datahub version 2.7 focuses on market-based load control and includes the load‑control functionality defined by the industry working group on market‑based load control. The working group, together with Datahub, produced a business specification for market-based load control. Its different versions, the latest being “Load control in Datahub 1.7”, have been published in document format in the Datahub service portal prior to being transferred to the wiki. For this reason, highlighting changes in the text with colour has not been considered necessary; instead, all changes are listed per page.

Changes in version 2.7

Changes in version 2.6

Development proposal #039

Datahub’s new authorization service.

5.11.2025 process maps added.

 

Development proposal #081

Datahub’s new authorization service.

5.11.2025 process maps added.

 

Development proposal #216

Datahub’s new authorization service.

5.11.2025 process maps added.

 

Development proposal #377

Datahub’s new authorization service.

5.11.2025 process maps added.

 

Development proposal #337

New processes for authorization requests.

14.10.2025 Corrected contents of messages F30 and F31 in accordance with the schema.

 

Development proposal #049

 

Development proposal #082

New interface for continuous delivery of metering data.

 

Development proposal #093

A supplier can cancel a retroactive agreement notification if the retroactive start requires handling by the supplier in the Datahub user interface.

 

Development proposal #110

The distribution system operator is notified of the termination of a sales agreement even in cases where the corresponding grid agreement has been terminated but has an open event for cancellation of the termination. In this case, the process does not create an open event for the termination of the grid agreement.

 

Development proposal #121

Event DH-344 has been removed.

  • DH-344 Grid agreement termination notification upon cancellation

 

Development proposal #199

A supplier can cancel a retroactive agreement notification if the retroactive start requires handling by the supplier in the Datahub user interface.

 

Development proposal #271

New instructions for updating the annual consumption estimate.

 

Development proposal #348

The Datahub operator can update a party’s business ID or name in the Datahub user interface, as long as the GLN remains unchanged.

 

Development proposal #351

Improving the flexibility of exchange point authorizations’ validity and renewal.

 

Development proposal #353

A notification is sent to the authorized party if the validity of the authorization is updated to match the agreement start date or is fully cancelled during the connection process.

 

Development proposal #364

Improving the flexibility of exchange point authorizations’ validity and renewal.

 

Development proposal #376

In the agreement termination cancellation process, authorizations are reinstated if the original agreement termination has ended or cancelled them.

 

Development proposal #384

Improving the flexibility of exchange point authorizations’ validity and renewal.

 

Development proposal #406

It is no longer possible for a party to submit a customer authorization notification on their own behalf (DH-811, DH-812, DH-813). Instead of these notifications, new authorization requests (DH-830 messages) must be used, and the customer must personally approve the authorization request sent by the party in the new Datahub authorization service.

  • DH-810 Customer’s authorization from a party

    • DH-811 Customer authorization notification – supplier

      • DH-811 Customer authorization notification (supplier)

    • DH-812 Customer authorization notification – third party

      • DH-812 Customer authorization notification (third party)

    • DH-813 Customer authorization notification – DSO

 

Development proposal #535

Changes required in the authorization processes due to the upcoming load control functionality.

 

Other changes