DH-211 Reporting metering data
Event description
A party responsible for metering (the DSO) reports the metering data for a metering point (accounting point, exchange point or production unit) to Datahub.
Parties
DSO
Datahub
Supplier
Third party
Time limits
Reporting metering data |
|---|
Time limits (time limits for reporting metering data, status processing and monitoring of metering data reports) must be observed, but corrections are permitted throughout the storage period for the metering data. |
Event processing in Datahub
Step | Description |
Metering point information on reactive power series availability | Datahub updates the value of the ‘reactive energy time series available’ accounting point attribute to ‘yes’ if reactive energy is reported for the accounting point and the attribute has the value ‘no’. |
Netting calculation | Datahub performs the netting calculation based on the metering data reported by the distribution system operator, provided that all metering data required for the calculation has been submitted to Datahub. The results of the calculation are forwarded to the parties entitled to the data. |
Energy community calculation | Datahub performs the energy community calculation based on the metering data reported by the distribution system operator, provided that all metering data required for the calculation has been submitted to Datahub. The results of the calculation are forwarded to the parties entitled to the data. |
Information storage
Origin of information | Information stored |
Information reported by the party | The metering data for the metering points and the the time period from which the data originates. |
Information processed by Datahub | Accounting point information on the availability of reactive power series. |
Return of information
Party | Description | Message |
|---|---|---|
DSO | Positive or negative acknowledgement for each transaction. Datahub rejects the message content on a per time series basis. This means that the entire message is not rejected due to a single error; only the time series containing errors are rejected. |
Forwarding of information
Party | Description | Note | Message |
|---|---|---|---|
Supplier | Metering data that Datahub receives and accepts is forwarded to the suppliers that have the rights to the information. Corrected time series data for a supplier’s agreement period will not be forwarded to the supplier if the supplier’s agreement has ended more than six weeks before the data reporting date. | The forwarded message contains two timestamps, when metering data is received in Datahub and when metering data is updated to database in Datahub. Metering data is forwarded using the unit with which the DSO has reported the metering data to Datahub. If the DSO reports the metering data for a time interval within which the invoice relevant information changes, Datahub splits the forward message into two transactions covering the periods before and after the time of the change. | |
Third party | Metering data that Datahub receives and accepts is forwarded to third parties that have the rights to the information. | ||
DSO | Metering data for exchange points is forwarded to the DSO of the exchange point’s other metering grid area, if it is another party than the party reporting the data. |
Significant errors and consequences
Possible metering errors and subsequent balance errors are processed in accordance with sections Correction of metering data and Management of balance deviation.
Event cancellation
Metering data is corrected by means of a new notification event.
Validation rules
Please see Datahub Validation Rules for a more thorough list.
Rule | Error code | Note |
|---|---|---|
A single notification event may contain a maximum of 10,000 metering time series and each metering time series may contain a maximum of 10,000 time-step values. | EC-MDM-PMV-001/ |
|
The metering point is recorded in the system. | EC-MDM-PTV-005 |
|
The party (distribution system operator or third party) is entitled to provide metering data to the metering grid area. | EC-MDM-PTV-021 |
|
The metering data resolution is the same as the time step reported for the metering point. | EC-MDM-VAL-INTERVAL |
|
The notified period is not in the future or more than 6 years in the past. | EC-MDM-PTV-018 |
|
The time series contains a value (or ‘Value absent’ information) for each position in the reporting period. | EC-MDM-PMV-003 |
|
The metering point is not in the ‘Under construction’ status. | EC-MDM-PTV-006 |
|
The transaction cannot consist of unchanged metering data (status and value) alone. | EC-MDM-VAL-DUPTRANS |
|
Metering data cannot be replaced with a weaker status. | EC-MDM-VAL-QUAL |
|
The value cannot be negative. | EC-MDM-VAL-RANGE |
|
Metering point-specific validation of measurements (not all of these rules are yet included in this table). |
|
|
|
|
|
Please observe that the list is not complete. | ||