DH-342 Notification of grid agreement cancellation

DH-342 Notification of grid agreement cancellation

image-20251017-121155.png
Notification of grid agreement cancellation

Event description

A DSO reports the cancellation of a grid agreement after having received a notification of sales agreement cancellation. The DSO cancels the grid agreement made on the basis of this sales agreement, or after having noticed an erroneous confirmation of a grid agreement.

Parties

  • DSO

  • Datahub

  • Supplier

Time limits

Reason for termination

Effective date of termination (= start date of the agreement to be cancelled)

Reason for termination

Effective date of termination (= start date of the agreement to be cancelled)

Agreement terminated by customer

Earliest termination date is 90 days in the future. Termination may be applied retroactively up to 1 year from the agreement start date.

Agreement terminated by supplier

Earliest termination date is 90 days in the future. Termination may be applied retroactively up to 10 years from the agreement start date.

Agreement terminated by DSO

Earliest termination date is 90 days in the future. Termination may be applied retroactively up to 10 years from the agreement start date.

Event processing in Datahub

Step

Description

Step

Description

Agreement information

The grid agreement is cancelled in the system according to the cancellation situation being processed. A possible previous grid agreement is restored if it was automatically terminated in connection with the cancelled agreement process and the DSO has not reported a separate termination for the previous grid agreement.

Terminating or cancelling authorizations

If the same customer no longer has a valid sales or grid agreement for the accounting point after the cancellation, the authorizations linked to the accounting point for the period of the cancelled agreement are cancelled or terminated on the start date of the cancelled agreement, if it is a retroactive cancellation and the authorization has begun before the start of the cancelled agreement.

Information storage

Origin of information

Information stored

Origin of information

Information stored

Information reported by party

Reason for grid agreement cancellation.

Information processed by Datahub

Grid agreement cancellation and possible restoration of a previous grid agreement.

Possible updates to the accounting point’s authorizations.

Return of information

Party

Description

Message

Party

Description

Message

DSO

Information about a successful event or rejected notification.

ACK

Forwarding of information

Party

Specification

Description

Message

Party

Specification

Description

Message

Supplier

Accounting point’s current supplier

Grid agreement cancellation information is forwarded to the supplier who has a valid sales agreement for the accounting point at the start of occurrence.

DH-342-2

Accounting point’s future supplier

Grid agreement cancellation information is forwarded to suppliers who have a sales agreement for the accounting point with a start date after the start of occurrence.

DSO

 

If a retroactively cancelled agreement remains valid for some time, Datahub notifies the DSO of the date from which the agreement is cancelled.

DH-342-3

Composite processes

Party

Description

Composite process

Party

Description

Composite process

Supplier

If there is an active sales agreement at the accounting point that corresponds to the cancelled grid agreement, the supplier must cancel it.

DH-342 → DH-341

Significant errors and consequences

Error

Consequence

Error

Consequence

The cancellation message is sent for the wrong accounting point and agreement.

The customer’s experience may be poor, and the matter may need to be clarified, for example, via email.

Event cancellation

The notification cannot be cancelled.

Validation rules

Please see Datahub Validation Rules for a more thorough list.

Rule

Error code

Note

Rule

Error code

Note

The accounting point is recorded in Datahub.

EC.MPT.115

 

The accounting point must not have the status ‘Removed from use’ or ‘Deleted’.

EC.MPT.120

 

Please observe that the list is not complete.