DH-221 Metering data request (supplier)
Message DH-221 (metering data request) is of message type F08.
Message payload includes the following information:
Information field | Level | Necessity | Field content | Note |
|---|---|---|---|---|
Payload | 1 | 1..1 |
|
|
Request period | 2 | 1..1 |
|
|
Start time | 3 | 1..1 |
|
|
End time | 3 | 1..1 |
|
|
Time step | 2 | 0..1 |
|
|
Invoice relevant | 2 | 0..1 |
| If the ‘Invoice relevant’ element is used in the request, the request must include the ‘Metering point type’ element with the value ‘F01’ (accounting point). |
Metering point | 2 | 1..1 |
|
|
Metering point type | 3 | 0..n |
| If the ‘Invoice relevant’ element is used in the request, the request must include the ‘Metering point type’ element with the value ‘F01’ (accounting point). |
Accounting point type | 3 | 0..n |
| If no type is given, both consumption and production accounting points’ data is returned. |
Metering point identification | 3 | 0..n |
| Either all metering points based on metering grid area or an individual metering point can be requested. If the request is carried out for individual metering points, the recommended maximum number of metering points in one search is 1000. |
Metering grid area identification | 3 | 0..n |
| Either all metering points based on metering grid area or an individual metering point can be requested. |
Product | 2 | 0..n |
|
|
Product identification | 3 | 1..1 |
|
|
Unit type | 3 | 1..1 |
| Active and reactive energy meterings may be requested in a specified unit. If no unit is given in the request, the corresponding active or reactive power is not returned. At least one of the units must be given for Datahub to return any data. |