DH-414 Cancellation of request for connection
Event description
A supplier reports a cancellation of a connection request it has sent earlier. The supplier requests the DSO to cancel the requested connection since the connection has been requested for the wrong accounting point or the accounting point no longer needs to be connected.
Parties
Supplier
Datahub
DSO
Time limits
Effective time of the update |
|---|
The start of occurrence cannot be in the past. |
Event processing in Datahub
Step | Description |
Cancellation of connection request | The connection request for the same accounting point with the same date no longer waits for the DSO to connect the accounting point. |
Return of information
Party | Description | Message |
|---|---|---|
Supplier | Notification of successful or rejected cancellation request. |
Forwarding of information
Party | Description | Message |
|---|---|---|
DSO | The cancellation request is forwarded to the accounting point’s DSO. |
Significant errors and consequences
Error | Consequence |
|---|---|
The cancellation is reported for the wrong connection request. | A customer’s electricity supply is not connected as requested. |
Event cancellation
The event cannot be cancelled.
Validation rules
Please see Datahub Validation Rules for a more thorough list.
Rule | Error code | Note |
|---|---|---|
The notified connection time is midnight. | EC.MPT.107 |
|
The accounting point is recorded in Datahub. | EC.MPT.115 |
|
The accounting point must not have the status ‘Removed from use’ or ‘Deleted’. | EC.MPT.120 |
|
The connection date is not in the past. | EC.MPT.125 |
|
The status of the accounting point reported in the message must be ‘Connected’. | EC.MPT.128 |
|
At the accounting point, there is a waiting connection request from the same supplier for the same date (the cancellation connection date matches the original requested connection date). | EC.MPT.153 | The connection request is considered pending as long as the DSO has not sent the DH-412 event. Delay notifications do not affect the status. |
The supplier must hold a valid sales agreement for the accounting point at the moment of sending the cancellation and for the cancellable connection date. | EC.AGR.238 |
|
Please observe that the list is not complete. | ||