DH-411 Request for supply connection

DH-411 Request for supply connection

image-20251020-072058.png
Request for supply connection

Event description

A supplier reports a request for accounting point supply connection to Datahub. The supplier requests the connection from the DSO when:

  • The customer pays the overdue invoice or rectifies another contractual breach

  • The supplier cancels the disconnection request on the requested disconnection date (a connection request is sent instead of the cancellation message DH-424).

Parties

  • Supplier

  • Datahub

  • DSO

  • Balancing service provider

Time limits

Effective time of the update

Effective time of the update

The start of occurrence is the current day or maximum 90 days in the future.

Event processing in Datahub

Step

Description

Closing previous connection and disconnection requests

If the same accounting point has an open connection or disconnection request from a supplier with a requested connection/disconnection date in the past, this request is closed so that it no longer waits for the DSO’s response.

Balance information update

If the connection request is reported for the same date as the supplier’s earlier disconnection request, the supplier’s balance information, which was terminated with the disconnection request, is linked to the supplier again.

Return of information

Party

Description

Message

Party

Description

Message

Supplier

Notification of successful or rejected connection request.

ACK

Forwarding of information

Party

Description

Message

Party

Description

Message

DSO

The connection request is forwarded to the DSO for the accounting point.

DH-411-2 

If the connection request changes a customer’s supplier information due to the updated agreement and the customer has issued an “Accounting point’s balance responsibility information” authorization for the accounting point, the new balance responsibility information is forwarded to the balancing service provider. The authorization must be valid on the reporting date of the event and the validity of the changed data must overlap with the validity of the authorization.

DH-136-2

Composite processes

Party

Description

Composite process

Party

Description

Composite process

DSO

The connection request is forwarded to the accounting point’s DSO.

DH-411 → DH-412

Significant errors and consequences

Error

Consequence

Error

Consequence

The connection request is reported for the wrong accounting point or the wrong day.

Depending on the DSO’s business processes, the DSO may contact the customer unnecessarily in order to ensure a safe connection.

Event cancellation

The cancellation is made with a separate connection request cancellation message (DH-414). The cancellation must be submitted before the DSO’s connection notification (DH-412).

Validation rules

Please see Datahub Validation Rules for a more thorough list.

Rule

Error code

Note

Rule

Error code

Note

The requested connection time is midnight.

EC.MPT.107

'00:00:00' (local) = '22:00:00' (UTC).

The accounting point is recorded in Datahub.

EC.MPT.115

 

The accounting point must not have the status ‘Removed from use’ or ‘Deleted’.

EC.MPT.120

 

The connection date is not in the past.

EC.MPT.125

 

No other connection process may be under way at the accounting point.

EC.MPT.127

 

The status of the accounting point reported in the message must be ‘Connected’.

EC.MPT.128

 

The supplier must have a valid supply agreement for the accounting point both at the time of submitting the request and on the connection date.

EC.AGR.214

 

 Please observe that the list is not complete.